Performance security and retention calculator
When you win, PPR 2025 asks for a performance security at a set share of the contract value, and holds back retention from your bills. Enter the contract value to see both, and how long they last.
The rule it uses
Goods: 10% of the contract value. Divisible commodities: 5%. Physical services: 5%. Works: 5%, where there is no arrangement for advance payment.
Public Procurement Rules, 2025 (SRO No. 388-Law/2025), rule 36(1); Schedule 2 (Bangladesh Gazette, 28 September 2025)
Works "of Tk 1 crore value": no performance security is needed. The schedule does not say "up to".
Public Procurement Rules, 2025 (SRO No. 388-Law/2025), Schedule 2, entry for rule 36(1) (Bangladesh Gazette, 28 September 2025)
Transport of goods: 5% of the contract value plus 5% of the value of the goods to be carried, which may also cover later transport.
Public Procurement Rules, 2025 (SRO No. 388-Law/2025), Schedule 2, entry for rule 36(1) (Bangladesh Gazette, 28 September 2025)
Intellectual and professional services: at most 3% to 5% of the contract value, at the rate set in the proposal documents; none for individual consultants.
Public Procurement Rules, 2025 (SRO No. 388-Law/2025), rule 36(9)-(10); Schedule 2 (Bangladesh Gazette, 28 September 2025)
If the evaluation committee finds a tender front-loaded or unbalanced, the contractual security can be raised to at most 25% of the contract value: 5% performance security and the rest as added retention.
Public Procurement Rules, 2025 (SRO No. 388-Law/2025), rule 36(2); Schedule 2 (Bangladesh Gazette, 28 September 2025)
Performance security stays valid until 28 days after the intended delivery or completion date, and is extended if that date moves.
Public Procurement Rules, 2025 (SRO No. 388-Law/2025), rule 36(5)-(6) (Bangladesh Gazette, 28 September 2025)
Retention: 5% deducted from each bill for works and physical services; 10% for domestic works contracts up to Tk 2 crore; 10% deducted from the final bill for goods.
Public Procurement Rules, 2025 (SRO No. 388-Law/2025), rule 37(1); Schedule 2 (Bangladesh Gazette, 28 September 2025)
Where no advance has been paid, retention and performance security together may not exceed 10% of the contract value, front-loaded tenders excepted.
Public Procurement Rules, 2025 (SRO No. 388-Law/2025), Schedule 2, entry for rule 37(1) (Bangladesh Gazette, 28 September 2025)
Retention is refunded within 28 days after the defects liability period ends.
Public Procurement Rules, 2025 (SRO No. 388-Law/2025), Schedule 2, entry for rule 37(2) (Bangladesh Gazette, 28 September 2025)
Under the limited tendering method, performance security is not compulsory.
Public Procurement Rules, 2025 (SRO No. 388-Law/2025), rule 80(5) (Bangladesh Gazette, 28 September 2025)
What it does not cover
- Contracts with an advance payment: Schedule 2 gives no works rate for them.
- Goods bought from a government, autonomous or semi-autonomous body with the government's own funds, where a deduction from the bills replaces the security (rule 36(1), second proviso).
- Spare parts bought directly from the original manufacturer or its sole agent, where performance security is not compulsory (rule 36(8)).
- International contracts, where the security must come from a scheduled bank in Bangladesh or a reputable bank with a correspondent bank here (rule 36(4)).
See every change behind these figures in the procurement rule tracker.
Common questions
What is the performance security for goods and works under PPR 2025?
Goods: 10% of the contract value. Divisible commodities: 5%. Physical services: 5%. Works: 5%, where there is no arrangement for advance payment.
How much retention money is held back from my bills?
Retention: 5% deducted from each bill for works and physical services; 10% for domestic works contracts up to Tk 2 crore; 10% deducted from the final bill for goods. Retention is refunded within 28 days after the defects liability period ends.
Do works of Tk 1 crore need performance security?
Works "of Tk 1 crore value": no performance security is needed. The schedule does not say "up to".
Guidance only, not legal advice. The tender document, its amendments and the official notice govern; where they differ from this page, follow them. Rules change: check BPPA's website for anything newer. Last checked: .
Find work worth preparing for.
Bring tender discovery, bid preparation and delivery into one workspace. Start a 7-day free trial today. No automatic charges.
Start your 7-day free trial